Tentative Schedule

A general schedule of key dates for the overall project is given below.

 
2000
2001
2002
2003
Task
W
Sp
Su
F
W
Sp
Su
F
W
Sp
Su
F
W
Sp
Su
F
Site  
Finalize site location                                
Site preparation                                
Site restoration                                
QA/QC  
Finalize QA/QC                                
Qual. Management Plan                                
Sampling  
Baseline                                
Intensives                                
Data Analysis  
Preliminary analysis                                
Hypothesis testing                                
Reporting  
Planning reports                                
Progress reports                                
Final report                                
Additional Studies  
Indoor Study                                
Epidemiology